MUSCAT INTERNATIONAL AIRPORT (SULTANATE OF OMAN)
Infrastructure Construction
Commencement Date:August, 2009
Estimated Completion Date:April, 2014
Facts & Figures:
New runway constructionarea:580,000 m2
Taxiway construction area:1,275,000 m2
Apron construction area:366,000 m2
Utility building area:24,000 m2
Total excavation volume:14,462,000 m3
Total backfill volume:17,464,000 m3
Concrete works:681,000 m3
Total asphalt works:1,202,000 tons
Piping works:1,346,000 m
Stone columns:840,000 m (Ø 850)
Total power set-up:278 MVA
Chiller plants with total capacity of:120 MW
Drainage structures with outflow capacity of:500 m³/second
Fuel farm capacity:30,000 m3
Other: 7 Bridges, Roundabouts and Road Connections to Airport
Total construction period:34 months (est.)
The Infrastructure Works for Muscat International Airport Development Project has been awarded to TAV – CCC Joint venture in August 2009. The duration of the project is 34 months, a challenge for a project this magnitude, which TAV Construction is familiar with.
The works comprise construction of the new runway, apron, power centers, utilities, landside and airside roads. One of the great challenges in building the new airport in Muscat is to provide adequate drainage of the area. The rainwater passes to get to the sea is the stretch of land on which the new runway will be as it is a flat, low-lying area, separated from the ocean only by a coastal road, where water can stagnate in the shallowest spots after powerful but short-lived downpours.
In order to prevent any effect of a possible flooding, the basement level of the terminal building has cancelled and all levels of the infrastructure works on the airfield, runways, apron and taxiway areas have been altered to suit. A several hundreds of meters wide “wadi channel” has been included within the scope of development works as well as three giant outlets with culvert connections with 500 m3 water capacity per second.