ADNAN MENDERES INTERNATIONAL AIRPORT (IZMIR, TURKEY)

New International Terminal and Car Park Construction
Commencement Date: May, 2005
Completion Date: September, 2006

Facts & Figures
Terminal design capacity:5,000,000 passengers per year
Total construction site area:418,000 m2
Terminal building area:110,000 m2
Apron area:150,000 m2
Car Park Area:64,000 m2 (2,200 vehicles)
Passenger boarding bridges:10 units
Check-in islands:6 units
Check-in counters:60 units (CUTE workstations)
Passport control counters:32 units
Elevators:36 units
Escalators:25 units
Travelators:26 units (2,952 linear meters)
Baggage claim carousels:6 units
Baggage handling system capacity: 4,800 baggages / hour
Total construction period:16 months

The original contract between TAV and the Turkish State Airport Authority (GHMI) called for the construction and operation of the new international terminal and car park at the Adnan Menderes International Airport in Izmir on a BOT basis. This Build-Operate-Transfer agreement specified an initial construction phase of 24 months followed by an operation period of six years and eight months. Since the complex was completed eight months earlier than the due date, the balance of eight months was added to the operational phase.

Following the start on July 2005, by using its special fast construction technology, TAV Construction completed the project in only 15 and ½ months.

TAV Construction’s futuristic and fast construction model can be fully recognized in new Adnan Menderes International Airport in Izmir. Perhaps the highlight of the airport is the terminal itself. Open and spacious, white steel beams and columns complement large glass walls, appropriately conveying the spectacular ambience of this breezy and sunny southwestern region of Turkey.
 
izmir_dom_04 izmir_int_01 izmir_int_02 izmir_int_04
 
 
 
 
  Interactive Map Site Map   TAV Tepe Akfen Investment Construction and Operation JSC Terms and Conditions